Development measures, June 17

Sunday, June 17, 2024:

Construction measures;

_ Staining the bricks on the floor and body of Alaghoundi Alley (Esta Ahmad and 1 freelance worker)

_ Completing the thatch covering of the side dead end of Alaghoundi Alley and implementing gutter 12 in the side alley at the end of Hosseiniyeh (Esta Reza and 1 freelance worker)

_ Completed the initial walls of Alaghoundi Pass

(Esta Shoja and 1 worker; Ruhollah)

_ Laying the path for the camera cable in the room adjacent to the Grand Mosque (1 cooperative worker)

_ Demolishing the damaged floor of Hosseiniyeh to renew the flooring (2 workers)

_ Grouting the paving stones of the alley behind Hosseiniyeh Saheb-e-Zaman and continuing the implementation of the brick plinth (Housing Foundation)

Follow-up and coordination;

_ Follow-up on securing funding from the Hamiyari Organization

_ Receiving a check for the payment for installing glass

_ Coordination and participation in preparing the content of the Fahraj page and website

 