Thursday, June 11, 2024:
Construction measures;
_ Implementation of mosaic carpet on the sidewalk adjacent to Hosseinieh (Esta Ahmad and 1 cooperative worker)
_ Continued implementation of the end cap, covering and decoration of the beginning of the side alley behind Hosseinieh by the Ecotourism (Esta Reza and 1 freelance worker)
_ Implementation of the end cap of the Ecotourism wall
(Esta Shoja and 1 worker; Abolfazl)
_ Preparation of straw and transportation to the work site (1 freelance worker and Ruhollah)
_ Continued implementation of the brick plinth (Housing Foundation)
_ Installation of scaffolding for the wall behind the Alaghvandi Dome
_ Completion of the decoration of the Alaghvandi Alley (cooperative worker)
Materials and tools;
Receiving a service (8 packages) of ordinary straw
Follow-up and coordination;
_ Follow-up on securing credit from the Cultural Heritage and Cooperation Organization
_ Follow-up and coordination on the installation of scaffolding
_ Ordering gypsum materials and stone powder and soil