Report on the measures taken to organize the Fahraj Cultural Axis from Saturday, July 2 to Thursday, July 7, 1403:
Development measures:
_ Completing the protective coating of the Alaghvandi dome, grouting the mosaic carpet on the Hosseiniyeh sidewalk, cooperating in the thatching of the Bumgardi alley and the tying of the honorifics (Esta Ahmad and 1 cooperative worker)
_ Completing the bottom and top covering of the side alley behind Hosseiniyeh from the Bumgardi, the tying of the walls of the main alley and the beginning of the Bumgardi alley (Esta Reza and 1 freelance worker; )
_ Implementing the bottom and top covering of the Bumgardi wall up to the beginning of the kitchen and the tying of the wall (Esta Shoja and 2 workers)
_ Preparing the thatch and transporting it to the work site (1 freelance worker and Ruhollah)
_ Continuing the implementation of the brick plinth in the main and side alley (Housing Foundation)
_ Installing scaffolding at the location of the mural painting and the eco-friendly wall
_ Continuing the tying of the Alahvandi alley (cooperative worker)
_ Scraping the cement coatings of the brick walls (cooperative worker)
Materials and tools:
Transfer of 3 sets of paving bricks to the workshop from the Dehyari warehouse
One set of sifted soil
One set of soil flowers
Rent of 10 masonry boards
Purchase of a pulley and 20-meter rope