Development measures, June 19

Wednesday, June 20, 2024:

Construction measures;

_Fixing the walls of Alaghvand Alley and the bathroom mesh and the parts with the main passage (Esta Ahmad and 1 cooperative worker)

_ Continuing the implementation of the bottom, covering and the wall of the beginning of the side alley behind Hosseiniyeh by the environmentalist (Esta Reza and 1 freelance worker)

_ Continuing the implementation of the bottom, covering and the wall of the middle wall of the side alley behind Hosseiniyeh

(Esta Shoja and 1 worker; Abolfazl)

_ Preparing thatch and transporting it to the work site (1 freelance worker and Ruhollah)

Follow-up and coordination;

_ Following up on securing funding from the Cooperation and Cultural Heritage Organization and the district administration

Follow-up and coordination;

_ Following up on securing funding from the Cooperation and Cultural Heritage Organization

_ Following up and coordinating the installation of scaffolding

_ Ordering plaster materials and stone powder and soil

 

 

 

 

 

 

 