Wednesday, June 20, 2024:
Construction measures;
_Fixing the walls of Alaghvand Alley and the bathroom mesh and the parts with the main passage (Esta Ahmad and 1 cooperative worker)
_ Continuing the implementation of the bottom, covering and the wall of the beginning of the side alley behind Hosseiniyeh by the environmentalist (Esta Reza and 1 freelance worker)
_ Continuing the implementation of the bottom, covering and the wall of the middle wall of the side alley behind Hosseiniyeh
(Esta Shoja and 1 worker; Abolfazl)
_ Preparing thatch and transporting it to the work site (1 freelance worker and Ruhollah)
Follow-up and coordination;
_ Following up on securing funding from the Cooperation and Cultural Heritage Organization and the district administration
Follow-up and coordination;
_ Following up on securing funding from the Cooperation and Cultural Heritage Organization
_ Following up and coordinating the installation of scaffolding
_ Ordering plaster materials and stone powder and soil