Development measures;
_ Participation in the thatch of the passage with Esta Shoja and staining the cement wall for mural painting (Esta Ahmad)
_ Continued the honorable work of the Boumgerdi Alley (Esta Reza and 1 freelance worker)
_ Continued the thatch of the Boumgerdi Alley wall (Esta Shoja and 2 freelance workers) _ Preparation of the thatch and transfer to the work site (1 freelance worker and Ruhollah)
_ Continued the sealing of the gutters and window drains of the Alaqundi Alley (cooperative worker)
_ Sealing the passage plinths and continuing the implementation of the plinth (Housing Foundation team)
Follow-up and coordination;
_ Continued the electrician’s work
_ Supply of materials for the Husseiniyeh
_ Securing the credit for the workshop in Khordad