Development measures, July 10

Sunday, July 10, 1403:

Development measures;

_ Participation in the thatch of the passage with Esta Shoja and staining the cement wall for mural painting (Esta Ahmad)

_ Continued the honorable work of the Boumgerdi Alley (Esta Reza and 1 freelance worker)

_ Continued the thatch of the Boumgerdi Alley wall (Esta Shoja and 2 freelance workers) _ Preparation of the thatch and transfer to the work site (1 freelance worker and Ruhollah)

_ Continued the sealing of the gutters and window drains of the Alaqundi Alley (cooperative worker)

_ Sealing the passage plinths and continuing the implementation of the plinth (Housing Foundation team)

Follow-up and coordination;

_ Continued the electrician’s work

_ Supply of materials for the Husseiniyeh

_ Securing the credit for the workshop in Khordad

 

 

Leave a Comment

Your email address will not be published. Required fields are marked *