Thursday, July 14, 2024:
Construction measures;
_ Continued thatching and thatching of the wall opposite the village (Esta Shoja and Esta Ahmad and 2 freelance workers)
_ Continued the maintenance of the village alley (Esta Reza and 1 freelance worker)
_ Preparation of thatching and transportation to the work site (1 freelance worker and Ruhollah)
_ Maintenance of the maintenance of the main passage and the beginning of the village alley (cooperative worker)
_ Removal of debris and excavation of the fence area with a tractor
_ Completion and improvement of the flooring of the path in front of the Alaqundi Mosque (Esta Habib team)
_ Continued installation of plinths and installation of plinths (Housing Foundation)
Follow-up and coordination;
_ Contract between the Cooperative Organization and the Cooperative Company
_ Financing the workshop for the month of Khordad
_ Follow-up on the continuation of furniture work