Development measures, July 14

Thursday, July 14, 2024:

Construction measures;

_ Continued thatching and thatching of the wall opposite the village (Esta Shoja and Esta Ahmad and 2 freelance workers)

_ Continued the maintenance of the village alley (Esta Reza and 1 freelance worker)

_ Preparation of thatching and transportation to the work site (1 freelance worker and Ruhollah)

_ Maintenance of the maintenance of the main passage and the beginning of the village alley (cooperative worker)

_ Removal of debris and excavation of the fence area with a tractor

_ Completion and improvement of the flooring of the path in front of the Alaqundi Mosque (Esta Habib team)

_ Continued installation of plinths and installation of plinths (Housing Foundation)

Follow-up and coordination;

_ Contract between the Cooperative Organization and the Cooperative Company

_ Financing the workshop for the month of Khordad

_ Follow-up on the continuation of furniture work