Performance report for the third week of Amrdad (20-25)
Saturday;
Preparing the installation site for signs Cleaning the passage from construction debris Providing materials for sealing (Esta Ahmad and Kargar Mohammad and Ruhollah)
Sunday; Dig and freeing the water area of the Bomgardi Alley Staining the cement wall at the beginning of the passage for painting (Esta Ahmad and Ruhollah) Completing the wall painting
Monday; Closed
Tuesday; Completing the sealing of the beginning of the passage after the Husseiniyeh, completing the remaining honorifics (Esta Ahmad and Kargar Fadlallah and Kargar Ruhollah) Painting the cement wall at the beginning of the alley
Wednesday; Removing the honorifics of Alaqundi Alley (Esta Ahmad and Kargar Fadlallah and Kargar Ruhollah) Completing the background color of the mural painting at the beginning of the alley
Thursday; Completion of the construction of the Alaqoundi Alley and the gutter behind the caravanserai (Ast. Ahmad and Ast. Fadlallah and Kargar Ruhollah)
Coordination; Completion of the electrical piping on the tourist route Completion of the installation of the mosque’s glass pillars Preparation of the performance report to date Communication with the official media of the province to cover the measures
Replacing a metal garage door with a colored shutter by the owner
Preparing a poorly landscaped cement wall for a second mural