اقدامات9و10و11مرداد

Development measures, August 9, 10, and 11

Tuesday, Wednesday and Thursday, 29, 30 and 40 August 1403:

Construction measures;

_Construction of a ramp at the entrance of the tourist restaurant, completion of the thatch covering and thatch covering of the walls of the tourist alley, staining the thatch in the required area, construction of a gutter in the house at the beginning of the passage after the Hosseiniyeh, completion of the plinth and lining of the passage; (Esta Ahmad and Esta Fazlallah and 2 freelance workers)

Continuation of mural painting

Materials; 200 carpet bricks from Dehyari

Coordinations;
_Completion of the remaining measures estimate
_ Preparation of a preliminary invoice for service furniture and valves
_ Preparation of a preliminary invoice for the required materials
_ Receiving an invoice for the construction of metal signs from the new contractor
_ Ordering materials for the improvement of the Hosseiniyeh flooring (concrete tiles)

Settlement of wages for July

اقدامات9و10و11مرداد
اقدامات9و10و11مرداد
اقدامات9و10و11مرداد
اقدامات9و10و11مرداد
اقدامات9و10و11مرداد
اقدامات9و10و11مرداد
اقدامات9و10و11مرداد
اقدامات9و10و11مرداد
اقدامات9و10و11مرداد
اقدامات9و10و11مرداد

Leave a Comment

Your email address will not be published. Required fields are marked *