Construction measures;
_ Repairing the gutters between the roof levels of the Jame Mosque and repairing the thatched roof of the bazaar next to the mosque (Esta Hassan and 1 worker)
_ Laying the entrance ramp of the Jame Mosque_ Sadat House _ The plinth around the Alahbandi Mosque (Esta Ahmad Fahrji and 1 worker)
_ Continuing to plaster and stain the main passage body (Esta Mohammadabadi and 1 worker)
_ Continuing to lay the brick foundation of the new path and laying the stone carpet floor (Housing Foundation)
_ Repairing the library arch (Esta Shoja and 2 workers)
_ Preparing the thatched roof (2 workers)
_ Preparing the floor and walls of the Alahbandi Mosque for the brick carpet floor (2 workers)
_ Plumbing the water and sewage of the water closet and toilets
_ Excavating the path of the electric pipe for lighting
_ Installing the first phase of the route guide signs on the road (road)

مصالح و ابزار؛
ماسه شسته؛ ۱ سرویس از همیاری
سنگ لاشه ؛ ۱ سرویس از بنیاد
ماسه بادی ؛ ۱ نیسان از شرکت تعاونی دهیاری ها
آجر فشاری ؛ ۱ سرویس از دهیاری

پیگیری و هماهنگی؛
_ پیگیری برق کار
_ پیگیری نظافت مسیر گردشگری سبز
_پیگیری حصارکشی دیوار تخریبی باغهای مسیر گردشگری سبز
_پیگیری تعویض لوله اب سوراخ شده کوچه اصلی حسینیه
_پیگیری تخریب کوچه فرعی کوچه کدخدا جهت تعویض لوله فاضلاب
_ پیگیری مصالح ادامه کار
مطالعات و طرح؛
بازبینی پرونده و لینک های قابل بارگذاری









