Construction Activities Performance Report Sundays, Mondays, Tuesdays, and Thursdays 14, 15, 16, and 18 Mordad 1403
Manpower; Asta Ahmad and Asta Fadlallah Worker Ruhollah and Worker Mohammad Hosseini
Actions; Roof flashing and floor and bodywork skirting after the Husseiniyeh Raising debris and cleaning the path Washing the remaining cement wall for painting
Materials; White cement and stone powder
Coordinations; Follow-up on securing the invoice for benches and supplying wood Follow-up on the completion of the tile panels Follow-up on receiving the advance invoice for pedestal lamps, service furniture, Husseiniyeh floor materials, and other materials required for the workshop